中文
 

Follow us 

Hot Topic
Market News
Events & Promo
Career Tips
Education News
Health & Life
State Grid Changzhou Power Supply Company Helps Accelerate Power Supply Supporting Facilities for CATL New Energy Project Again
PRNewswire

State Grid Changzhou Power Supply Company Helps Accelerate Power Supply Supporting Facilities for CATL New Energy Project Again

Publish date: 26 Oct 2026

Follow us

Stay updated on the job market

Popular Articles

【35歲後的頂級財富】港人公認人生贏家10大清單:你做到幾多個?
【35歲後的頂級財富】港人公認人生贏家10大清單:你做到幾多個?
【QS亞洲大學排名】港5大學強勢列入10強!港大蟬聯亞洲榜首,城大超中大首登全港第二
【QS亞洲大學排名】港5大學強勢列入10強!港大蟬聯亞洲榜首,城大超中大首登全港第二
【天氣轉涼】天文台:今晚急跌明早最低16度!新界溫差極大,打工仔出門必備「洋蔥式著法」
【天氣轉涼】天文台:今晚急跌明早最低16度!新界溫差極大,打工仔出門必備「洋蔥式著法」
【辦公室職業病】Office 工最易中嘅四大職場傷患!入嚟睇吓你有無中招(附預防自救法)
【辦公室職業病】Office 工最易中嘅四大職場傷患!入嚟睇吓你有無中招(附預防自救法)
【AI 衝擊打工仔】最新調查:逾半港人憂AI令退休前景更難預測!「飯碗不保」恐打破傳統退養規劃
【AI 衝擊打工仔】最新調查:逾半港人憂AI令退休前景更難預測!「飯碗不保」恐打破傳統退養規劃

CHANGZHOU, China, Oct. 26, 2026 /PRNewswire/ -- Recently, the N10 to N11 section of the 220 kV line project from Ganxi to Shidai Xinke carried out work crossing the Nanjing-Hangzhou High-Speed Railway for the first time. State Grid Changzhou Power Supply Company used drones to send guide ropes across the high-speed railway twice in succession, preparing for the subsequent deployment of the first ground wire and one phase conductor respectively. This section, the most difficult and highest-risk along the entire line, has thus entered the stage of stringing work across the high-speed railway, laying the foundation for the subsequent completion and connection of the line.

The project is located in Liyang, Changzhou, Jiangsu. The line runs from Ganxi Substation to the planned Shidai Substation and is erected with double-circuit lines on the same tower. Among them, the span between the two towers N10 and N11 is 469 meters, crossing in sequence along the line direction a 110 kV line, the Nanxi River, the G25 Changchun-Shenzhen Expressway, and the Nanjing-Hangzhou High-Speed Railway. Multiple crossings are concentrated within the same span, so construction must take into account both the protection of existing power lines and the river channel, as well as expressway traffic and compliance with railway operation arrangements. It is a key section of the entire line's construction.

The railway construction window is scheduled from 0:00 to 4:00 each day. Railway blockade, confirmation of catenary power outage and grounding, and final inspections must all be completed within the window, leaving only three hours for the main stringing procedures, and the procedures in each nighttime window must be closely coordinated.

To use the limited window for key procedures, the project team of State Grid Changzhou Power Supply Company carried out preparatory work in advance. The two towers N10 and N11 were erected first, the tensioning site, crane positioning, and crossing protection were arranged according to the plan, and tools and communication equipment were checked item by item. Before formal operations, on-site personnel re-verified equipment, personnel, and safety conditions, and clarified the tasks for each position that night.

The guide rope crossing the expressway was first sent across during the daytime, so when the nighttime railway window opened, a guide rope was already in place to receive it at the expressway crossing section. In the early morning, after the railway construction permit was issued and the catenary power outage and grounding were confirmed, construction personnel used drones to send the primary guide rope across the high-speed railway. According to the on-site arrangements, the conductors of the two circuits and the two ground wires are planned to complete crossing deployment over four nights. Subsequently, tensioning equipment will pull the ropes level by level, completing the deployment and tensioning and attachment of conductors and ground wires in batches.

Chu Guowei, Director of the Project Management Center of State Grid Changzhou Power Supply Company, introduced that the CATL New Energy Phase VI project plans to build cell production lines as well as module and battery pack assembly lines, with an expected electricity load of approximately 210,500 kW. After the project is completed and commissioned, the two 220 kV circuits will connect Ganxi Substation with the enterprise user substation. According to the connection plan, when one circuit is withdrawn, the other circuit has the capacity to bear the entire load of the project, providing dual-circuit power supply assurance for the project's production.

Follow us

Stay updated on the job market

Popular Articles

【35歲後的頂級財富】港人公認人生贏家10大清單:你做到幾多個?
【35歲後的頂級財富】港人公認人生贏家10大清單:你做到幾多個?
【QS亞洲大學排名】港5大學強勢列入10強!港大蟬聯亞洲榜首,城大超中大首登全港第二
【QS亞洲大學排名】港5大學強勢列入10強!港大蟬聯亞洲榜首,城大超中大首登全港第二
【天氣轉涼】天文台:今晚急跌明早最低16度!新界溫差極大,打工仔出門必備「洋蔥式著法」
【天氣轉涼】天文台:今晚急跌明早最低16度!新界溫差極大,打工仔出門必備「洋蔥式著法」
【辦公室職業病】Office 工最易中嘅四大職場傷患!入嚟睇吓你有無中招(附預防自救法)
【辦公室職業病】Office 工最易中嘅四大職場傷患!入嚟睇吓你有無中招(附預防自救法)
【AI 衝擊打工仔】最新調查:逾半港人憂AI令退休前景更難預測!「飯碗不保」恐打破傳統退養規劃
【AI 衝擊打工仔】最新調查:逾半港人憂AI令退休前景更難預測!「飯碗不保」恐打破傳統退養規劃

Hottest Tags

#35歲後的頂級財富
#人生贏家清單
#精神內耗
#準時收工
#健康生活
#職場減壓
#生活掌控權
#網民熱話
#QS亞洲大學排名
#香港大學排名
#港大蟬聯第一
#城大創歷史新高

Contact Us
Notice
Back to Top
We use cookies to enhance your experience on our website. Please read and confirm your agreement to our Privacy Policy and Terms and Conditions before continue to browse our website. Read and Agreed